Below you will see three versions of the after action reports. The original version is just the way I received it with no changes.

The cleaned version is a copy of the original version with all the stray marks, smudges, etc removed. I found some pages in the originals that were up-side-down. That was corrected on the clean version.

On the restored version I converted the oringinal PDF pages to Microsoft Word so I could replace any weak or hard to read letters, words and sometimes a string of words. I tried to be careful but there is a chance I may have typed in something wrong. If you see something that doesn't look or sound right you can compare it against the original PDF document. I then converted the repaired Microsoft Word pages back to PDF format. If you find any mistakes please let me know so I can fix the errors.

 

More of these after action reports are available on the 39th Engineer Battalion Alumni wep site at: http://39thengrbn.com

 

My e-mail address is: rbm39d@twc.com

 

-----------------------------------------------------------

After Action Report of Operation Geronimo I - Adams (first phase)

Date of operations: 31 October - 27 December 1966
Location: Tuy Hoa
Orginazation: 39th Engr Bn (C)(A) (Hq Co, A Co, B Co, C Co)
Mission: Battalion provides combat support for FWMF in area; clears route 7B from TUY HOA to CUNG SON and keeps road open; upgrades QL #l to Class 50 one-way traffic from TUY HOA to TUY AN; upgrades airfield at CUNG SON to take C-123 traffic; clears route 6B from QL #1 to TL 2D. Battalion also constructs POL line extension from HAO SON to TUY HOA South Airfield and POL pumping station (PORT LANE); and executes other construction missions as directed.

Original
Cleaned
Restored

-----------------------------------------------------------

Operation Report - Lessons Learned for Period Ending January 1967

This document shows what the the 39th Engineer Battalion and it's three line companies (A, B and C) were doing before the arrival of my company, Company D. Company D arrived in Vietnam in February 1967. This document includes some detailed information about how the enemy places their mines and how we searced for them.

Original
Cleaned
Restored

-----------------------------------------------------------

Operation Baker/Malheur I

Date of operation: 10 April 1967 to 31 May 1967
Location: Duc Pho
Part of: TASK FORCE OREGON

Original
Cleaned
Restored

-----------------------------------------------------------

 

Operation Multnomah and Lake

Date of operation: 24 May 1967 9 July 1967
Location: Duc Pho
Part of: TASK FORCE OREGON
Mission: Open up Highway QL1 and road from Duc Pho to beach for convoy traffic.

Original
Cleaned
Restored

------------------------------------------------------------

 

Operation Report - Lessons Learned for Period Ending 30 April 1967

Includes when Company D arrived in Vietnam and became a part of 39th Engineer Battalion.

Original
Cleaned
Restored

------------------------------------------------------------

 

Operation Report - Lessons Learned for Period Ending 31 July 1967

Original
Cleaned
Restored

------------------------------------------------------------

 

Operation Report - Lessons Learned for Period Ending 31 January 1968

Includes Company D move from Duc Pho to Chu Lai and LZ Baldy

Original
Cleaned
Restored

------------------------------------------------------------